The Resource Histogram shows the work load for a single resource or a group resource for the period of elapsed time covered by the project. It is created from information you provide about resources, tasks, and dates in the project’s schedule.
-- part contents for card part 10
----- text -----
1 of 2
-- part contents for background part 28
----- text -----
Resource Histogram
-- part contents for background part 27
----- text -----
The Nine Charts
-- part contents for card part 11
----- text -----
The resource’s work load. This resource’s work load exceeds its number available, so the resource is over-allocated.
-- part contents for card part 12
----- text -----
The number available. A value of 1.00 indicates a single resource working full time (as determined by the resource’s calendar).